Questions related to IGBC AP Examination
Q
|
What does IGBC stand for?
|
Ans
|
Indian Green Building Council
|
Q
|
Which was the first green building in India?
|
Ans
|
CII –Sohrabji Godrej Green Business Center, Hyderabad
|
Q
|
Which website can you get information about green buildings and the Indian Green Building Council?
|
Ans
| |
Q
|
Which credit and how many points are awarded to a project with IGBC AP as a principal design team member Innovation ?
|
Ans
|
Only one point is awarded under Innovation and Design Module
|
Q
|
Who can become members of IGBC ?
|
Ans
|
· Organisation (as a founder member)
· Organisation (as an annual member)
· Individual Member (Any Arch, Engineer, consultant)
|
Q
|
Which member of the team needs to be an IGBC member for the project to claim the discount?
|
Ans
|
Any team member who is involved in project design / operation/ consultant
|
Q
|
Name the 4 Green rating systems available in India through IGBC
|
Ans
|
· IGBC Green New Buildings rating system
· IGBC Green Existing Buildings rating system
· IGBC Green Factory rating system
· IGBC Green Homes rating system
|
Q
|
Name the 2 Green rating systems that recently launched by IGBC
|
Ans
|
· IGBC Green Healthcare rating system (Draft for Public Comments)
· IGBC Green Data Center rating system
|
Q
|
What is the most recommended time for a project register for rating through IGBC?
|
Ans
|
Initial or at Design Stage to get tangible and intangible benefits benefits of all the mandatory requirements and Credits requirements
|
Q
|
At which stage should a project select the rating system the project will be following?
|
Ans
|
Feasibility study
|
Q
|
Where can the fees be found for registration / certification for an IGBC rating system?
|
Ans
|
At www.igbc.in and particular page of rating system
|
Q
|
Which area should not be considered in calculation of fees?
|
Ans
|
Air-Conditioned and Non-air-conditioned area shall be considered. Parking area shall not be considered
|
Q
|
What is the next stage after the registration form is submitted on IGBC website?
|
Ans
|
Study particular rating system and call for Project team that includes Architect, Engineers, Planners, landscape architect, consultant, simulation expert, energy specialist, etc.
|
Q
|
What does the project team receive once a project is get registered with IGBC ?
|
Ans
|
Thank you mail highlighting Project Reference No. for future correspondence, reference guide & IGBC templates, specific to rating system registration
|
Q
|
What is a CIR?
|
Ans
|
Credit Interpretation Ruling
|
Q
|
What steps should you take before filing a CIR?
|
Ans
|
Check the intent, requirement, calculation details in reference Guide. Also, check the previously logged CIR’s in the CIR page of IGBC website
|
Q
|
With registration, how many CIR’s does project receive for free and how much do subsequent CIRS cost?
|
Ans
|
2 CIR’s are free of cost & later 5000 per CIR
|
Q
|
Where can you find other project CIR’s?
|
Ans
| |
Q
|
What is Pre Certification?
|
Ans
|
Pre-certification helps in marketing the particular project. Mostly, builders try to marketise their project to sell the space and also to ensure high quality of built environment.
|
Q
|
Which rating systems can you apply for Pre certification?
|
Ans
|
· IGBC Green Homes rating system
· IGBC Green New Buildings rating system
· IGBC Green Healthcare rating system
|
Q
|
Can a project be denied credits in pre-certification submittal?
|
Ans
|
Yes, it is possible.
|
Q
|
If a project achieves “Gold” rating in pre-certification, can it apply for Platinum in final certification?
|
Ans
|
Yes, upgradation helps projects in achieving better rating and tangible benefits. All the projects can get recertification every after three year.
|
Q
|
How often should project team update IGBC on status of project after pre-certification?
|
Ans
|
Every 6 months
|
Q
|
If a project is achieving 45 credits and missing one Prerequisite, can it still apply for certification?
|
Ans
|
No. Mandatory requirement or Prerequisite must be met for Certification/ Pre-certification of project
|
Q
|
What items should be submitted with the application for certification?
|
Ans
|
All building drawings, Filled in Templates, Calculations along with Fee. All the documents shall be submitted as per the guideline/ rating system for every mandatory requirement and Credit requirement.
|
Q
|
How long does IGCB take to perform preliminary review?
|
Ans
|
30 working days
|
Q
|
What is a clarification
|
Ans
|
Reply to the project team for the preliminary review report highlighting Credits and mandatory requirement including awarded, pending & Denied credits.
|
Q
|
What are the contents of Preliminary Review report?
CAA (Credit Accept Anticipated, Pending & Denied
|
Ans
| |
Q
|
Where are the fees available for certification and what are the fees based on?
|
Ans
|
http://www.igbc.in & fees shall be calculated based on the built-up area in sq ft excluding parking.
|
Q
|
Is there a discount for IGBC members?
|
Ans
|
IGBC does not offer any discount on certification fee. Only founding member / annual member (project owner/ developer only) would get discount in certification/ pre-certification fee
|
Q
|
How much time is given for project team to respond to Preliminary review?
|
Ans
|
All review, Pre-certification and Certification would be returned in 30 working days
|
Q
|
How many credits / prerequisites does the IGBC verify on site?
|
Ans
|
Site visit is planned for every project. During site visit, all the features implemented at site are evaluated and verified.
|
Q
|
Name the 2 stages at which on site inspection takes place?
|
Ans
|
During construction & before awarding the final certification
|
Q
|
On receiving the final review, what are the options for a project team?
|
Ans
|
Accept or appeal for certification
|
Q
|
How long does a project team have to appeal
|
Ans
|
15 working days
|
Q
|
How much does an appeal cost?
|
Ans
|
Rs. 20,000/credit
|
Q
|
Who reviews an Appeal? What documents should be submitted?
|
Ans
|
Other than the first reviewed party all relevant documents related to that credit alone with all drawings & narration (original submittal for the credit)
|
Q
|
What does a “certified” project receive from IGBC?
|
Ans
|
10 original Certificates, Award letter & a metal plague. For additional plaque, project has to pay charges separately
|
Q
|
What is the difference between CIR and Clarification?
|
Ans
|
CIR- requires details from IGBC Raised by project team answered by IGBC
Clarification-Project team reply for the IGBC during preliminary review
|
Q
|
On which website can you find the information on certified projects and accredited individuals of IGBC in India?
|
Ans
| |
Q
|
How many copies (soft & hard) of documents need to be sent to IGBC?
|
Ans
|
2 sets Soft copy
|
Q
|
What are the major chapters in IGBC Green Buildings rating system ?
|
Ans
|
1. Sustainable Site Planning (SSP)
2. Water efficiency (WE)
3. Energy Efficiency (EE)
4. Indoor Environment Quality (IEQ)
5. Building Material & Resources (BMR)
|
Q
|
What are the 4 levels of LEED certification a project can achieve?
|
Ans
|
Platinum, Gold, Silver, Certified
|
Q
|
Is erosion and sedimentation control mandatory for an IGBC Green rated projects?
|
Ans
|
Yes
|
Q
|
Which type of projects can IGBC Green EB rating system be applied to?
|
Ans
|
All existing building projects
|
Q
|
What is a major renovation?
|
Ans
|
More than 50% renovation (Envelope, HVAC & Electrical system)
|
Q
|
What does erosion and sedimentation control helps to protect?
|
Ans
|
Protect the top soil, air pollution reduce, improve water quality
|
Q
|
Is addressing construction stage for erosion & sedimentation sufficient?
|
Ans
|
No
|
Q
|
What are the different types of seeding?
|
Ans
|
Temporary & Permanent
|
Q
|
What impact does mulching have?
|
Ans
|
Retains moisture & protect top soil
|
Q
|
Name 4 structural controls to E&S?
|
Ans
|
Earth dike, Silt fencing, Sediment trap, Sediment basin
|
Q
|
Which Indian standard is followed for Erosion & Sedimentation Control?
|
Ans
|
NBC part 10, chapter 1, section -4
|
Q
|
What types of sites are inappropriate for green buildings?
|
Ans
|
Prime Farm land, Within 100 feet of wet land (ENVIS) Habitat of endangered species (WII) & Public parkland
|
Q
|
What is a farmland?
|
Ans
|
Produce crops with less damage to resources, least cost, Best place for produce food, crop, Acceptable acidity/alkalinity, salt, sodium Adequate & dependable water, No rock or less rock
|
Q
|
Who lists endangered species in India?
|
Ans
|
Wild life institute of India
|
Q
|
What is the minimum distance between site and wet land?
|
Ans
|
100 feet
|
Q
|
Is development on parkland appropriate?
|
Ans
|
No
|
Q
|
What is the minimum density onsite and in calculated radius to achieve SSC2?
|
Ans
|
1.38 FAR ½ mile radius 60,000 sq.ft / acre
|
Comments